Coverage

The Map below shows the draft Super Fast Broadband Intervention Area Coverage across the Black Country (2015 – 2017).  Please note, the next stage of the process is for BT to undertake planning and survey work, which will take until mid-2015 and the first high speed fibre services will become available towards the end of 2015.  

Formal deployment of the scheme has started with structures being erected across the Black Country. During the project, 431 cabinets will be upgraded over 6 phases, resulting in 49,841 Total Homes Passed (THP) being delivered.

Unfortunately, until survey work has been completed we are unable to comment on specific locations or on any Exchange.  Once surveying is complete for each phase, the Intervention Coverage area across the Black Country will be confirmed.